We carry out regular reviews and works on our high-rise buildings.
Current activity
Our principal contractor, Higgins, is currently in the processes of completing property surveys and investigations.
If you are a resident, please contact Higgins to book an appointment for your property survey.
Watch our video introducing the survey
Timescales
- Investigations will be finished at the end of July 2026.
- The final scope of works will be revied and confirmed by August 2026.
- August to November 2026 - Preparation of our application to the building safety regulator.
- Approval from Regulator anticipated by April 2027.
- Contractor to start on each site between May and June 2027.
- The building work to continue between June and July 2027.
| Address | Planned works list |
|---|---|
Delta Estate
|
|
Petra Estate
|
|
|
|
Consultation events
Havering’s Building safety roadshow resident consultation events have been organised to meet with residents and discuss all things building safety.
The events will bring together Havering’s Compliance and Fire Safety Teams along with the Planned Works Team and our appointed principal contractor, Higgins.
The events will give residents the opportunity to share any feedback, concerns and provide suggestions to us.
Confirmed dates
- 14 July 2026- Kipling / Dryden Towers, 3pm to 6pm
- 28 July 2026 – Delta estate, Gidea park, 3pm to 6pm.
- 29 July 2026 – Petra estate, Hornchurch, 3pm to 6pm.
Contact us about building safety works
We understand that you may have some queries regarding our planned safety works to your building.
If you do, please do not hesitate to contact us directly for a chat or e-mail us anytime. We will always get back to you.
- Higgins Team - Higgins Resident Liaison Officer - 07798 677034 - haveringfsw@higginspartnerships.co.uk
- Havering Team - 01708 431466 / 07516 478499 - resident.liaison@havering.gov.uk